Aishwarryam Construction Updates

As on August 2017



 

General Points

  • Project Entrance Arch Work - 100 % Completed
  • Paver block works for the Entire setback area of the project – 100 % completed.
  • External services like Electrical cabling, Plumbing for the Metro water sump , Rain water harvesting, Electrical trenches, and Plumbing trenches – 100 % completed.
  • Specific Transformer for entire Aishwarryam project – 100 % completed.
  • Fencing works for the Transformer – 100 % Completed

  • Electrical room, Association room & Ground floor lobby works - 100 % completed.

  • Flooring works for the all the corridors (Front & Rear blocks) – 100 % completed.

  • Car park marking – In progress

  • Children’s play area work – 65 % Completed & Equipments planning under progress

  • Lift – Block 2 Completed and in operation / Block – 1 – In progress

Handing over strategy 

  • 35 clients have already occupied – In.

  • 12 flats handing over – In progress

  • 29 flats handed over to landlords.

  • Over – all Project handing over under progress

Construction photos will be updated once in a month.